Project timeline

The preparation of the MUNI BioPharma Hub project, funded by the National Recovery Plan (NRP) of the Czech Republic, has started in 2021 and is scheduled to be completed in June 2026.

  • 04/2021–05/2021

    • Start of project implementation with the assumption of NRP funding
    • Selection of a contractor for the project documentation
    • Signing a contract with the general designer
  • 06/2021–02/2022

    • Preparation of project documentation for territorial proceedings
    • Preparation of a public tender for technical supervision of the investor
  • 03/2022–02/2023

    • Preparation of project documentation for building permit procedure and documentation for the selection of a building contractor
  • 05/2023–07/2023

    • Selection of a general building contractor
  • 08/2023–12/2025

    • Construction of the building of BioPharma Hub
    • Implementation of public tenders for direct and other supplies
    • Start of pilot operation
  • 01/2026–06/2026

    • Pilot operation of the building
    • Completion of the project funded by NRP